The Challenge

Regent House, a multi-tenanted commercial building in central London, required a comprehensive M&E upgrade to improve energy performance, meet current building regulations, and attract premium tenants. The existing electrical infrastructure was at capacity, the lighting was inefficient and poorly controlled, and the HVAC system was costly to run and maintain. All works had to be carried out in a live building with multiple occupied floors.

02

Our Solution

We delivered a phased M&E refurbishment: upgraded the main electrical distribution with new sub-mains and tenant metering, installed a full LED lighting retrofit with daylight harvesting and occupancy sensors, replaced the aging HVAC plant with high-efficiency VRV systems, and installed a new addressable fire alarm system throughout. A new BMS was commissioned to centralise control and provide energy reporting. Phasing allowed tenants to remain operational throughout.

03

The Outcome

The refurbishment achieved a measured 42% reduction in energy consumption and helped the building achieve an improved EPC rating, directly supporting the client's leasing strategy. Tenant comfort and satisfaction improved significantly, and the new BMS provides ongoing energy optimisation. The project was completed with zero lost-time incidents across 20 weeks of works in a live environment.

42%

Energy Reduction

20 wks

Project Duration

2 grades

EPC Rating Improvement

Services Delivered

Electrical Distribution Upgrade
LED Lighting Retrofit
VRV HVAC Systems
Addressable Fire Alarm
BMS Commissioning
Tenant Metering

Project Gallery

Reception desk and Group Room entrance01 — Reception desk and Group Room entrance
Reception desk with blush countertop and Group Room entrance02 — Reception desk with blush countertop and Group Room entrance
Corridor with Therapy Room doors and ENGAGED indicators03 — Corridor with Therapy Room doors and ENGAGED indicators
Office corridor with IT Server Room and Therapy Room 2 signage04 — Office corridor with IT Server Room and Therapy Room 2 signage
Hallway with Therapy Room 1 & 2 doors and kitchenette area05 — Hallway with Therapy Room 1 & 2 doors and kitchenette area
Clinic room with mint green accent wall and vision-panel door06 — Clinic room with mint green accent wall and vision-panel door
Office space with vertical blinds and emergency pull-cord trunking07 — Office space with vertical blinds and emergency pull-cord trunking
Clinic room door with air con reminder notice and Panasonic AC unit08 — Clinic room door with air con reminder notice and Panasonic AC unit
Small vacant office room with window and vertical blinds09 — Small vacant office room with window and vertical blinds
Clinical consult room with emergency call system pull-cord10 — Clinical consult room with emergency call system pull-cord
IT server room with server rack and Panasonic AC unit11 — IT server room with server rack and Panasonic AC unit
Reception desk with curved pink countertop and Group Room entrance12 — Reception desk with curved pink countertop and Group Room entrance
L-shaped reception desk with privacy screen and Group Room doors13 — L-shaped reception desk with privacy screen and Group Room doors
Empty room with fire exit door and emergency release controls14 — Empty room with fire exit door and emergency release controls
Group Room double doors with access card reader15 — Group Room double doors with access card reader
Empty office room with mint green accent wall and structural column16 — Empty office room with mint green accent wall and structural column
Corridor with double doors and ceiling air conditioning cassette17 — Corridor with double doors and ceiling air conditioning cassette
Empty consulting room with vertical blinds and natural light18 — Empty consulting room with vertical blinds and natural light
Corridor with double doors and emergency door release call point19 — Corridor with double doors and emergency door release call point
Fire exit door with extinguishers and evacuation signage20 — Fire exit door with extinguishers and evacuation signage
Reception desk with corridor view through Group Room doorway21 — Reception desk with corridor view through Group Room doorway
Office room with cable trunking, vertical blinds and emergency push button22 — Office room with cable trunking, vertical blinds and emergency push button
Office corner with mint green accent wall and power trunking23 — Office corner with mint green accent wall and power trunking
Door with nurse call console, fire extinguishers and emergency release24 — Door with nurse call console, fire extinguishers and emergency release
Sage green wall with wall-mounted heater and emergency door release25 — Sage green wall with wall-mounted heater and emergency door release
Office corner with emergency alarm pull-cord and window overlooking red brick buildings26 — Office corner with emergency alarm pull-cord and window overlooking red brick buildings
Office room with emergency pull-cord alarm and vertical blinds27 — Office room with emergency pull-cord alarm and vertical blinds
Wall trunking detail with nurse call unit and power outlets28 — Wall trunking detail with nurse call unit and power outlets
Narrow hallway with card reader, fire alarm call point and Staff Office door29 — Narrow hallway with card reader, fire alarm call point and Staff Office door
24/7 Emergency Support

Got an urgent M&E issue? We're here around the clock.

01296 256901(Option 1)

Have a similar project in mind?

Let's discuss how we can deliver the same level of quality and reliability for your next M&E project.

Start a Project
Get a Quote